Bridge and Roadway Pavement Rehabilitation, Indianapolis, IN

Rieth-Riley Construction Co., Inc. (Rieth-Riley), was awarded this project

August 13, 2018. This project included HMA overlay, preventative

maintenance, concrete pavement restoration, pavement patching, bridge

maintenance and bridge repair on I-465 from I-65 to I-70 on the Westside,

approximately 9 miles in each direction.  Major items of work included

14,955 tons of QC/QA HMA, 1,505 ton of SMA, 15,314 SFT of partial depth

joint repair, 1,812 SYS of 12” reinforced concrete bridge approaches, and

bridge deck patching. The contract specifications defined an accelerated

schedule that detailed complete closures of the east and westbound lanes

of I-465. Each direction of I-465 were detailed to be individually closed and

completed within 9 days and 8 hours (224 hours) to meet the schedule

requirements. Rieth-Riley utilized 31 different crews from their Indianapolis

and Cal-Region areas along with their equipment resources to deliver the

completed project ahead schedule.

 

Completed in 9 days and 8 hours (ahead of schedule)

Use of 31 different Crews

Contractor: Rieth-Riley Construction 

Owner: INDOT

Related Projects

LaPorte County Roads

Rieth-Riley paves and resurfaces LaPorte’s County Roads regularly. This project was completed in 2018 and we continue to pave roads as a preferred contractor in

Read More »

Request a Quote

Contact our team of experts for a free quote!
Scroll to Top